RAPID/Roadmap/Geo/Sections
Roadmap Coverage
The roadmapping initiative covers the states show in green on the map below, including California, Nevada, Hawai'i, Alaska, Idaho, Utah, Oregon, Montana,Colorado, and Texas. The roadmap is being developed at the federal and state levels, allowing for future expansion to the local (county) level. Development of the roadmap for four additional states (Washington,New Mexico,Arizona, and Wyoming) is underway for Fiscal Year 2014.
Click on a state to view Regulatory Roadmap information specific to that state.
List of Roadmap Sections
The flowcharts listed below were developed as part of the Geothermal Regulatory Roadmap project. The flowcharts cover the major requirements for developing geothermal energy, including, land access, exploration and drilling, plant construction and operation, transmission siting, water resource acquisition, and relevant environmental considerations. We are continuously adding flowcharts and improving this site. Check back often for new flowcharts and updates.
Reading the Roadmap
The flowcharts are divided into General, Federal, and State columns to allow for ease of use. To use the flowcharts, start with General Flowchart for Section 1, or jump to the General Flowchart for a section you are interested in. These General Flowcharts will lead you to the federal and state flowcharts you will need. The overview flowchart on the right will help you decide where to begin.
- For more information on reading these flowcharts, Visit the "Getting Started" Section.
- The GRR is continually being updated and added to. Some flowcharts have not yet been developed, but placeholders have been created. If you have input on any of these processes, please feel free to login to make updates, or .
Disclaimer
The flowcharts have been reviewed by relevant agency, developer and legal personnel, and are meant to serve as a guide to obtaining the permits needed for geothermal power plant development and a way to communicate the process among interested parties. This website is not intended to constitute legal advice or the provision of legal services and none of the individuals or agencies involved in developing this document warrant or certify that the information on this page is accurate. The services of a competent professional should be sought if legal or other specific expert assistance is required.
Overview Flowcharts
1: Land Use Planning Overview
2: Site Considerations
3: Land & Geothermal Resource Access Overview
4: Exploration Permitting Overview
5: Drilling Overview
6: Construction Permits Overview
7: Power Plant Siting, Construction, and Regulation Overview
8: Transmission Siting & Interconnection Overview
9: Environmental Overview
10: On-Site Evaluation Process
11: Cultural Resource Assessment
12: Biological Resource Assessment Process
13: Land Use Assessment Process
14: Water Resource Assessment
15: Air Quality Assessment Process
16: Geological Resources Assessment Process
17: Aesthetic Resource Assessment
18: Waste and Hazardous Material Assessment Process
19: Water Access & Water Rights Overview
20: Plant Decommissioning Overview
Federal Flowcharts
1-FD-a: BLM Land Use Planning Process
1-FD-b: BLM Land Use Plan Amendment Process
1-FD-c: USFS Land Use Planning Process
1-FD-d: USFS Land Use Plan Amendment Process
3-FD-a: Federal Geothermal Land Leasing
3-FD-b: Tribal Land Leasing
3-FD-c: Right-of-Way Access
3-FD-d: Forest Service Special Use Authorization
3-FD-e: Bureau of Reclamation Use Authorization
4-FD-a: Exploration Application Process BLM
4-FD-b: Exploration Pre-Application Process (NV only)
4-FD-c: Exploration Application Process USFS
4-FD-d: BLM Exploration Operations
5-FD-a: Drilling Application Process
5-FD-b: Drilling Pre-Application Process NV only
6-FD-a: Storm Water Construction General Permit
7-FD-a: Utilization Application Process
7-FD-b: Plant Commissioning Process
7-FD-c: PURPA Qualifying Facility Certification Process
7-FD-d: Exempt Wholesale Generator Status Process
8-FD-a: FERC Order No. 2003 Process for Interconnection
8-FD-b: FERC Order No. 792 Process for Interconnection
9-FD-a: BLM NEPA Process
9-FD-b: BLM Environmental Assessment (EA) Process
9-FD-c: BLM Environmental Impact Statement (EIS) Process
9-FD-d: BLM Appeals Process
9-FD-e: DOE NEPA Process
9-FD-f: DOD NEPA Process
11-FD-a: NHPA Section 106 - Resource Survey
11-FD-b: Tribal Consultation
11-FD-c: NHPA Section 106 - Assessment of Adverse Effects
11-FD-d: NHPA Section 106 - Resolution of Adverse Effects
12-FD-a: Migratory Bird Considerations
12-FD-b: Bald & Golden Eagle Permit
12-FD-c: ESA Section 7 Consultation Process
12-FD-d: ESA Section 10 Incidental Take Permit
12-FD-e: National Marine Fisheries Service Marine Mammal Protection Act Incidental Harassment Authorization Process
12-FD-f: National Marine and Fisheries Service Marine Mammal Protection Act Incidental Take Letter of Authorization Process
12-FD-g: Fish and Wildlife Service Marine Mammal Protection Act Incidental Harassment Authorization Process
12-FD-h: Fish and Wildlife Service Marine Mammal Protection Act Incidental Take Letter of Authorization Process
13-FD-a: Farmland Evaluation Process
13-FD-b: Military Land Evaluation
13-FD-c: Bridge Permit Application Process
13-FD-d: Aeronautical Considerations
13-FD-e: Rivers and Harbors Act Section 10 Permitting Process
13-FD-f: DOD Clearinghouse Mission Compatibility Evaluation Process
14-FD-a: Clean Water Act Section 404 Permit Application Process
14-FD-b: EPA NPDES Permitting Process
14-FD-c: EPA UIC Process
17-FD-a: Wild & Scenic Rivers 7(a)
18-FD-a: CERCLA Process
18-FD-b: Aboveground Storage Tank
18-FD-c: Brownfield Grant Application
20-FD-a: Well Abandonment Process
State Flowcharts
- 1-AK-a: Land Use Planning
- 1-CA-a: Land Use Planning
- 1-CO-a: Land Use Planning
- 1-HI-a: Land Use Planning
- 1-ID-a: Land Use Planning
- 1-MT-a: Land Use Planning
- 1-NM-a: Land Use Planning
- 1-NV-a: Land Use Planning
- 1-OR-a: Land Use Planning
- 1-TX-a: Land Use Planning
- 1-UT-a: Land Use Planning
- 1-WA-a: Land Use Planning
- 3-AK-a: State Competitive Mineral Leasing Process
- 3-AK-b: State Right of Way Process
- 3-AK-c: State Encroachment Process
- 3-AK-d: State Noncompetitive Mineral Leasing Process
- 3-AK-e: Land Use Permit
- 3-AK-g: Utility Permit to Construct on ADOT&PF ROW
- 3-AK-h: Alaska Native Claims Settlement Lands Leasing
- 3-CA-a: State Geothermal Lease
- 3-CA-b: State Land Right of Way
- 3-CA-c: Encroachment Permit
- 3-CO-a: State Geothermal Lease
- 3-CO-b: State Right of Way Process
- 3-CO-c: State Encroachment Process
- 3-CO-d: State Access Permit Process
- 3-CO-e: State Utility or Special Use Permit Process
- 3-HI-a: Reserved Land Leasing Process
- 3-HI-b: State Mineral Leasing Process
- 3-HI-c: State Encroachment Process
- 3-HI-d: Use and Occupancy Permit
- 3-HI-e: Permit to Construct Upon a State Highway ROW
- 3-HI-f: Permit to Cross or Enter the State Energy Corridor
- 3-ID-a: State Lands Commercial Geothermal Lease
- 3-ID-b: State Land Access Overview
- 3-ID-c: State Encroachment Process
- 3-ID-d: Land Use Permit
- 3-ID-e: Term Easement
- 3-MT-a: State Geothermal Lease
- 3-MT-b: State Land Lease
- 3-MT-c: State Encroachment Process
- 3-MT-d: Land Use License Process
- 3-MT-e: Encroachment Permit
- 3-MT-f: Right-of-Way Easement for Utilities
- 3-NM-a: State Geothermal Lease
- 3-NM-b: State Right of Way Easement
- 3-NM-c: State Encroachment Process
- 3-NM-d: State Business Lease
- 3-NM-e: Right of Entry / Temporary Access Permit
- 3-NM-f: Public Highway Utility Accommodation Permit
- 3-NM-g: Permit to Construct Access Opening on Public ROW
- 3-NV-a: State Land Leasing Process and Land Access
- 3-NV-b: State Land Overview
- 3-NV-c: State Encroachment Process
- 3-NV-d: State Land Lease
- 3-NV-e: State Land Right of Way
- 3-OR-a: Oregon State Geothermal Lease
- 3-OR-b: Easements on Trust and Non-Trust Land
- 3-OR-c: State Encroachment Process
- 3-OR-d: Competitive Geothermal Lease
- 3-OR-e: Noncompetitive Geothermal Lease
- 3-TX-a: State Geothermal Lease
- 3-TX-b: State Land Access
- 3-TX-c: State Encroachment Overview
- 3-TX-d: Lease of Permanent School Fund Land
- 3-TX-e: Lease of Texas Parks & Wildlife Department Land
- 3-TX-f: Lease of Land Trade Lands
- 3-TX-g: Lease of Relinquishment Act Lands
- 3-TX-i: Highway Right of Way Lease
- 3-UT-a: State Geothermal Lease
- 3-UT-b: State Easement Process
- 3-UT-c: State Encroachment Process
- 3-UT-d: Geothermal Steam Lease (Utah Non-Trust Lands)
- 3-UT-e: Geothermal Steam Lease (Utah Trust Lands)
- 3-UT-f: Encroachment Permit
- 3-UT-g: Grant of Access Permit
- 3-WA-a: State Geothermal Lease
- 3-WA-b: Land Access Overview
- 3-WA-c: Transmission Line Right of Way
- 3-WA-d: State Land Lease
- 3-WA-e: Access Across State Lands
- 4-AK-a: State Exploration Process
- 4-AK-b: Geophysical Exploration Permit
- 4-AK-c: Geothermal Exploration Permit
- 4-CA-a: State Exploration Process
- 4-CO-a: State Exploration Process
- 4-HI-a: State Exploration Process
- 4-ID-a: State Exploration Process
- 4-MT-a: State Exploration Process
- 4-NM-a: State Exploration Process
- 4-NV-a: State Exploration Process
- 4-NV-b: Temporary Use of Ground Water for Exploration
- 4-NV-c: Monitoring Well Waiver
- 4-OR-a: State Exploration Process
- 4-OR-c: Geothermal Prospect Well Process
- 4-OR-d: Exploration Injection Permit
- 4-TX-a: State Exploration Process
- 4-UT-a: State Exploration Process
- 4-WA-a: State Exploration Process
- 5-AK-a: Drilling and Well Development
- 5-CA-a: Drilling and Well Development
- 5-CO-a: Drilling and Well Development
- 5-HI-a: Drilling and Well Development
- 5-ID-a: Drilling and Well Development
- 5-MT-a: Drilling and Well Development
- 5-NM-a: Drilling and Well Development
- 5-NV-a: Drilling and Well Development
- 5-NV-b: Sundry Notice
- 5-OR-a: Drilling and Well Development
- 5-TX-a: Drilling and Well Development
- 5-UT-a: Drilling and Well Development
- 5-WA-a: Drilling and Well Development
- 6-AK-a: Transportation Permit
- 6-AK-b: Construction Storm Water Permit
- 6-AK-c: Drinking Water Permit
- 6-CA-a: Transportation/Oversized Load Permit
- 6-CA-b: Construction Storm Water Permit
- 6-CO-a: Extra-Legal Vehicle Permitting Process
- 6-CO-b: Construction Storm Water Permit
- 6-HI-a: Oversize and Overweight Vehicles and Loads Permit
- 6-HI-b: Construction Storm Water Permit
- 6-HI-c: Drinking Water Permit
- 6-HI-d: Oversize and/or Overweight Vehicles and Loads Permit
- 6-HI-e: Boiler Pressure Vessel Permit
- 6-ID-a: Transportation Permit
- 6-ID-b: Construction Storm Water Permit
- 6-ID-c: Drinking Water Permit
- 6-MT-a: Montana Overdimensional or Overweight Load Permit
- 6-MT-b: Construction Storm Water Permit
- 6-MT-c: Drinking Water Permit
- 6-MT-d: Other Overview
- 6-MT-e: Floodplain Development Permit
- 6-MT-f: Short-term Water Quality Standard for Turbidity (318 Authorization)
- 6-NM-a: Special Permit for Excessive Size or Weight
- 6-NM-b: Construction Storm Water Permit
- 6-NV-a: Transportation Permit
- 6-NV-b: Construction Stormwater Permit
- 6-NV-c: Drinking Water Permit
- 6-OR-a: Transportation Permit
- 6-OR-b: Construction Storm Water Permit
- 6-OR-c: Drinking Water Permit
- 6-TX-a: Extra-Legal Vehicle Permitting Process
- 6-TX-b: Construction Storm Water Permit
- 6-UT-a: Transportation Permit
- 6-UT-b: Storm Water Permit
- 6-UT-c: Drinking Water Permit
- 6-WA-a: Oversize-Overweight Load Permit
- 6-WA-b: Construction Storm Water Permit
- 6-WA-d: Hydraulic Project Approval Permit
- 7-AK-a: Power Plant Siting Process
- 7-AK-c: Certificate of Public Convenience and Necessity
- 7-CA-a: State Plant Commissioning Process - Application for Certification
- 7-CA-b: State Plant Commissioning Process - Small Power Plant Exemption
- 7-CA-c: California Energy Facility CPUC Process
- 7-CA-d: CPCN for Non-AFC Facilities
- 7-CO-c: Certificate of Public Convenience and Necessity
- 7-HI-a: Geothermal and Cable System Development Permit
- 7-HI-b: Renewable Energy Facility Siting Process
- 7-HI-c: Certificate of Public Convenience and Necessity
- 7-ID-a: Power Plant Siting Process
- 7-ID-c: Certificate of Convenience and Necessity
- 7-MT-a: Energy Facility Siting
- 7-NM-c: Certificate of Public Convenience and Necessity
- 7-NV-a: Permit to Construct and Permit to Operate
- 7-NV-c: Certificate of Public Convenience and Necessity
- 7-OR-a: State Plant Construction
- 7-OR-b: State Plant Commissioning Process
- 7-OR-d: Expedited Plant Commissioning Process
- 7-TX-a: Energy Facility Registration
- 7-TX-b: REC Generator
- 7-TX-c: Certificate of Convenience and Necessity
- 7-UT-a: Power Plant Siting Process
- 7-UT-c: Certificate of Public Convenience and Necessity
- 7-WA-a: Power Plant Siting Process
- 8-AK-c: Certificate of Public Convenience and Necessity
- 8-AZ-a: Transmission Siting Process
- 8-CA-a: California Transmission Siting Process
- 8-CA-b: CAISO Interconnection Request Process
- 8-CA-c: CPUC Process for Transmission Facilities
- 8-CA-d: Certificate of Public Convenience and Necessity
- 8-CA-f: Permit to Construct Power Lines
- 8-CO-a: Transmission Siting Process
- 8-CO-c: Certificate of Public Convenience and Necessity
- 8-HI-c: Transmission Line Approval
- 8-ID-c: Certificate of Public Convenience and Necessity
- 8-ID-e: State NIETC Route Approval Process
- 8-MT-a: Transmission Siting Process
- 8-NM-a: Transmission Siting Process
- 8-NM-b: Interconnection of Generating Facilities over 10MW
- 8-NM-c: Certificate of Public Convenience and Necessity
- 8-NM-d: State Determination of Right of Way Width Process
- 8-NM-f: Interconnection up to and Including 10MW
- 8-NV-c: Certificate of Public Convenience and Necessity
- 8-NV-d: Special Use Permit for Utilities
- 8-OR-a: Transmission Siting Process
- 8-OR-c: Certificate of Public Convenience and Necessity
- 8-TX-a: Transmission Siting Process
- 8-TX-b: ERCOT Interconnection
- 8-TX-f: Distributed Generation Interconnection
- 8-UT-a: Transmission Siting Process
- 8-UT-c: Certificate of Public Convenience and Necessity
- 8-WA-a: Transmission Site Certification
- 9-AK-a: State Environmental Review Process
- 9-CA-a: State Environmental Review Process
- 9-HI-a: State Environmental Review Process
- 9-HI-b: Hawaii EA Process
- 9-HI-c: Hawaii EIS Process
- 9-ID-a: State Environmental Review Process
- 9-MT-a: State Environmental Review Process
- 9-NV-a: State Environmental Review Process
- 9-OR-a: State Environmental Review Process
- 9-UT-a: Energy Pre-Design Meeting Process
- 9-WA-a: State Environmental Overview
- 9-WA-b: State Environmental Review
- 9-WA-c: State Environmental Impact Statement
- 11-AK-a: State Cultural Considerations
- 11-CA-a: State Cultural Considerations
- 11-CO-a: State Cultural Considerations Overview
- 11-CO-b: Human Remains Process
- 11-HI-a: State Historical Preservation Review
- 11-ID-a: State Cultural Considerations
- 11-MT-a: State Cultural Considerations Overview
- 11-MT-b: Human Remains Process
- 11-MT-c: Cultural Resource Discovery
- 11-NM-a: State Cultural Considerations Overview
- 11-NM-b: Cultural Resource Investigation Process
- 11-NM-c: Human Burial Discovery Process
- 11-NM-d: Cultural Resource Discovery Process
- 11-NV-a: State Cultural Considerations
- 11-OR-a: State Cultural Considerations
- 11-TX-a: State Cultural Considerations Overview
- 11-TX-b: Human Remains Process
- 11-TX-c: Cultural Resource Discovery Process
- 11-UT-a: State Cultural Considerations
- 11-WA-a: State Cultural Considerations Overview
- 11-WA-b: Human Remains Process
- 11-WA-c: Archaeological Resource Discovery Process
- 12-AK-a: State Biological Resource Considerations
- 12-CA-a: California Fish and Game Process
- 12-CO-a: State Biological Considerations
- 12-HI-a: Habitat Conservation Plan and Incidental Take License
- 12-ID-a: State Biological Resource Considerations
- 12-MT-a: State Biological Resource Considerations
- 12-NM-a: State Biological Resource Considerations
- 12-NV-a: State Biological Resource Considerations
- 12-OR-a: State Biological Resource Considerations
- 12-OR-b: Fish and Wildlife Habitat Mitigation Policy
- 12-TX-a: State Biological Resource Considerations
- 12-UT-a: State Biological Resource Considerations
- 12-WA-a: Live Wildlife Taking Permit
- 12-WA-b: State Trust Lands Habitat Conservation Plan Compliance
- 13-AK-a: State Land Use Assessment
- 13-CA-a: State Land Use Assessment Process
- 13-CA-b: Coastal Land Use Assessment
- 13-CA-c: Coastal Zone Federal Consistency
- 13-HI-a: Conservation District Use Permit
- 13-ID-a: State Land Use Assessment
- 13-MT-a: State Land Use Assessment
- 13-NV-a: State Land Use Assessment
- 13-TX-a: State Land Use Assessment
- 13-WA-a: Coastal Zone Management Federal Consistency Determination
- 14-AK-a: Nonpoint Source Pollution
- 14-AK-b: Alaska Pollutant Discharge Elimination System Permit
- 14-AK-c: Underground Injection Control Permit
- 14-AK-d: 401 Water Quality Certification
- 14-AZ-b: AZPDES Permit
- 14-CA-a: Nonpoint Source Pollution
- 14-CA-b: NPDES Permit
- 14-CA-c: Underground Injection Control Permit
- 14-CA-d: 401 Water Quality Certification
- 14-CA-e: Waste Discharge Requirements
- 14-CO-a: Nonpoint Source Pollution
- 14-CO-b: Colorado Discharge Permit System (CDPS)
- 14-CO-c: Underground Injection Control Permit
- 14-CO-d: 401 Water Quality Certification
- 14-CO-e: Ground Water Discharge Permit
- 14-HI-a: Nonpoint Source Pollution
- 14-HI-b: NPDES Permit
- 14-HI-c: Underground Injection Control Permit
- 14-HI-d: 401 Water Quality Certification
- 14-ID-a: Nonpoint Source Pollution
- 14-ID-b: NPDES Permit
- 14-ID-c: Underground Injection Control Permit
- 14-ID-d: 401 Water Quality Certification
- 14-ID-f: 401 NPDES Water Quality Certification
- 14-MT-a: Nonpoint Source Pollution
- 14-MT-b: MPDES Permit
- 14-MT-c: Underground Injection Control Permit
- 14-MT-d: 401 Water Quality Certification
- 14-MT-e: Groundwater Pollution Control System
- 14-NM-a: Nonpoint Source Pollution
- 14-NM-b: NPDES Permit
- 14-NM-c: Underground Injection Control Permit
- 14-NM-d: 401 Water Quality Certification
- 14-NM-e: Ground Water Discharge Permit
- 14-NV-a: Nonpoint Source Pollution
- 14-NV-b: NPDES Permit
- 14-NV-c: Underground Injection Control Permit
- 14-NV-d: 401 Water Quality Certification
- 14-NV-e: Groundwater Discharge Permit
- 14-OR-a: Nonpoint Source Pollution
- 14-OR-b: NPDES Permit
- 14-OR-c: Underground Injection Control Permit
- 14-OR-d: 401 Water Quality Certification
- 14-OR-e: Water Pollution Control Facility Permit
- 14-OR-f: Onsite Wastewater Management
- 14-TX-a: Nonpoint Source Pollution
- 14-TX-b: NPDES Permit
- 14-TX-c: Underground Injection Control Permit
- 14-TX-d: 401 Water Quality Certification
- 14-TX-e: Ground Water Discharge Permit
- 14-UT-a: Nonpoint Source Pollution
- 14-UT-b: Utah Pollutant Discharge Elimination System
- 14-UT-c: Underground Injection Control Permit
- 14-UT-d: 401 Water Quality Certification
- 14-UT-e: Ground Water Quality Protection Permit
- 14-UT-f: UPDES Antidegradation Review
- 14-WA-b: NPDES Permit
- 14-WA-c: Underground Injection Control Permit
- 14-WA-d: 401 Water Quality Certification
- 14-WA-e: State Wastewater Discharge Permit
- 15-AK-a: Air Quality Assessment Process
- 15-AK-b: Air Quality Permit - Minor Permit
- 15-AK-c: Air Quality Permit - Title V Operating Permit
- 15-CA-a: Air Quality Permit - Authority to Construct
- 15-CA-b: Air Quality Permit - Operating Permit
- 15-CO-a: Air Quality Permit
- 15-HI-a: Air Quality Permit - Air Pollution Control Permit
- 15-ID-a: Air Quality Permit - Permit to Construct
- 15-ID-b: Air Quality Permit - Tier II Operating Permit
- 15-MT-a: Air Quality Permit
- 15-NM-a: Air Quality Permit - Construction Permit
- 15-NM-b: Air Quality Permit - Accelerated Construction Permit Review
- 15-NM-c: Air Quality Permit - Operating Permit
- 15-NV-a: Air Quality Permit - Operating Permit
- 15-OR-a: Air Quality Permit - Air Contaminant Discharge Permit
- 15-TX-a: Air Quality Permit - Permit to Construct
- 15-UT-a: Air Quality Permit
- 15-WA-a: Air Quality Permit - Notice of Construction Permit
- 15-WA-b: Air Quality Permit - Operating Permit
- 17-AK-a: Aesthetic Resource Assessment
- 17-CA-a: State Aesthetic Concerns
- 17-HI-a: Noise Permit
- 17-ID-a: Aesthetic Resource Assessment
- 17-MT-a: Aesthetic Resource Assessment
- 17-MT-b: Montana Stream Protection Act (SPA 124 Permit)
- 17-MT-c: Natural Streambed and Land Preservation Act (310 Permit)
- 17-MT-d: Streamside Management Zone Law
- 17-NV-a: Aesthetic Resource Assessment
- 17-OR-a: Aesthetic Resource Assessment
- 18-AK-a: Underground Storage Tank Permit
- 18-AK-b: Hazardous Waste Permit
- 18-AK-c: Waste Disposal Permit Process
- 18-CA-b: Hazardous Waste Permit
- 18-CO-a: Underground Storage Tank Permit
- 18-CO-b: Hazardous Waste Permit
- 18-HI-a: Underground Storage Tank Permit
- 18-HI-b: RCRA
- 18-HI-c: Wastewater Treatment
- 18-HI-d: Variance from Pollution Control
- 18-HI-e: Chemical Inventory Reporting
- 18-ID-a: Underground Storage Tank Permit
- 18-ID-b: Hazardous Waste Permit
- 18-ID-c: Wastewater Pretreatment Permit
- 18-ID-d: Solid Waste Management Facilities
- 18-MT-a: Underground Storage Tank Permit
- 18-MT-b: Hazardous Waste Facility Permit
- 18-NM-a: Underground Storage Tank Process
- 18-NM-b: Hazardous Waste Permit Process
- 18-NV-a: Underground Storage Tank Permit
- 18-NV-b: State RCRA Process
- 18-NV-c: Waste Disposal Permit
- 18-OR-a: Underground Storage Tank Permit
- 18-OR-b: Hazardous Waste Permit
- 18-TX-a: Underground Storage Tank Permit
- 18-UT-a: Underground Storage Tank Permit
- 18-UT-b: Hazardous Waste Permit
- 18-WA-a: Underground Storage Tank Permit
- 18-WA-b: Dangerous Solid Waste Permit
- 19-AK-a: Water Access and Water Rights
- 19-AK-b: Temporary Use of Water Permit
- 19-AK-c: Permit to Appropriate
- 19-CA-a: Water Access and Water Rights
- 19-CA-b: Permit to Appropriate Water
- 19-CA-c: Groundwater Considerations
- 19-CA-d: Change in Ownership of Water Right
- 19-CA-e: Petition to Change an Existing Water Right
- 19-CA-f: Short Term Water Transfer Process
- 19-CA-g: Long Term Water Transfer Process
- 19-CO-a: Water Access and Water Rights Overview
- 19-CO-b: Denver Basin Permitting Process
- 19-CO-c: Designated Ground Water Basin Well Permitting Process
- 19-CO-d: Water Well Permit
- 19-CO-e: New Water Right Process for Surface Water and Tributary Ground Water
- 19-CO-f: Substitute Water Supply Plan
- 19-CO-g: Colorado Water Right Adjudication Process
- 19-CO-h: Denver Basin and Designated Basin Permitting Process
- 19-CO-i: Determination of Nontributary Ground Water Status
- 19-HI-a: Surface Water Use Permit
- 19-ID-a: Water Access and Water Rights
- 19-ID-b: Change Application Process
- 19-MT-a: Water Access and Water Rights
- 19-NM-a: Water Access and Water Rights Overview
- 19-NM-b: Permit to Drill a Well with No Consumptive Use of Water
- 19-NM-c: Permit to Change an Existing Water Right
- 19-NM-d: Considerations for Water Use in Restricted Basins
- 19-NM-e: Water Access on State Trust Lands Process
- 19-NM-f: Permit for Temporary Water Use
- 19-NM-g: Guidelines for Deep Groundwater Appropriation
- 19-NM-h: Permit to Appropriate Water
- 19-NM-i: Change in Ownership of Water Right
- 19-NM-j: Impairment Analysis Process
- 19-NV-a: Water Access and Water Rights
- 19-NV-b: Appropriation and Change of Use Process
- 19-OR-a: Water Access and Water Rights
- 19-TX-a: Water Access and Water Rights Overview
- 19-TX-b: New Water Right Process For Surface Water and Ground Water
- 19-TX-c: Surface Water Permit
- 19-TX-d: Transfer of Surface Water Right
- 19-TX-e: Temporary Surface Water Permit
- 19-UT-a: Water Access and Water Rights
- 19-WA-a: Water Access and Water Rights Overview
- 19-WA-b: New Water Right Permit Process
- 19-WA-c: Transfer or Change of Water Right
- 19-WA-d: Water Conservancy Board Transfer or Change of Water Right
- 19-WA-e: Water Well Notice of Intent for New Well
- 19-WA-f: Water Well NOI for Replacement or Additional Wells
- 20-AK-a: Well Abandonment Process
- 20-CA-a: Well Abandonment Process
- 20-HI-a: Well Abandonment Process
- 20-ID-a: Well Abandonment Process
- 20-MT-a: Well Abandonment Process
- 20-NM-a: Well Abandonment Process
- 20-NV-a: Well Abandonment Process
- 20-OR-a: Well Abandonment Process