Once the lead agency is determined, it is responsible for continuing forward with environmental review. In Washington, environmental review is effectuated through the completion of an Environmental Checklist by the developer, which assists the lead agency in determining whether the proposal will likely result in negative impacts to the environment.


State Environmental Assessment Process

9-WA-b.1 to 9-WA-b.2 – Provide Developer with Environmental Checklist

The lead agency will supply an Environmental Checklist for the developer to fill out. WAC 197-11-960. The Environmental Checklist is a standard form used by all agencies to obtain information about a proposal. The form includes questions about the proposal, its location, possible future activities, and questions about potential impacts of the proposal on each element of the environment.

The lead agency may fill out the checklist, or require the developer to do so. WAC 197-11-315(4). However, it is recommended that the developer complete the environmental checklist so that they may examine the proposal from an environmental perspective. The checklist was designed to be as generic as possible to ensure that it is applicable to every kind of proposal. SEPA Online Handbook § 2.5.1.


9-WA-b.3 – Conduct Environmental Review

The lead agency will use the information provided in the environmental checklist to review the probable environmental impacts that will result from the project.


9-WA-b.4 to 9-WA-b.5 – Does a Categorical or Statutory Exemption Apply?

A proposed project may be categorically exempt under WAC 197-11-800 – 890 (except as limited by WAC 197-11-305) or statutorily exempt under RCW 43.21C. If the project is exempt, the lead agency does not make a threshold determination or establish EIS requirements and the developer may continue with the project. WAC 197-11-800; RCW 43.21C.


9-WA-b.6 to 9-WA-b.8 – Review Application Materials

The lead agency must independently evaluate the developer’s responses, and must conduct an initial review of the environmental checklist without requiring additional information from the developer. Following the initial review, the lead agency may request additional information from the developer. WAC 197-11-100.


9-WA-b.9 – Make Threshold Determination of Environmental Impacts

“Threshold Determination” means the decision by the lead agency whether or not an EIS is required for a proposal. WAC 197-11-797. A threshold determination is required for any proposal that may be defined as an “action” under WAC 197-11-704, and that is not categorically exempt (WAC 197-11-800 – 890) or statutorily exempt (RCW 43.21C). This determination is subject to limitations concerning proposals for which a threshold determination has already been issued. WAC 197-11-310. All threshold determinations must result in either a determination of non-significance (DNS) or a determination of significance (DS). WAC 197-11-310.

Agencies must use the Environmental Checklist to assist in making their threshold determinations for the proposal. WAC 197-11-315(1). The lead agency will use the environmental checklist and any additional information requested to determine if the proposal is likely to have a probable significant adverse environmental impact and to consider mitigation measures that the developer will implement as part of the proposal. WAC 197-11-330. The SEPA rules encourage all lead agencies to solicit comments from agencies with expertise to evaluate the environmental impacts of a proposal. WAC 197-11-335. These consultations can assist the lead agency in determining permits required, appropriate mitigation, any additional information and/or studies, and when an environmental impact statement is or is not needed for a proposal. SEPA Online Handbook § 2.5.2.

A threshold determination for a proposal must be made no later than 90 days after the application and supporting documentation are determined to be complete. The developer may request an additional 30 days for the threshold determination. RCW 43.21C.033; WAC 197-11-310(3).


9-WA-b.10 to 9-WA-b.11 – Will There Be a Significant Adverse Impact on the Environment?

Following the completion of the Environmental Checklist and environmental review, if the lead agency determines the project will not have a probable adverse impact on the environment the lead agency will complete a Determination of Non-Significance (DNS). WAC 197-11-970.

If the lead agency determines that the project will have a significant adverse impact on the environment, initiate the State Environmental Impact Statement process:

State Environmental Impact Statement:
9-WA-c


9-WA-b.12 – Draft Determination of Non-Significance (DNS)

The decision to prepare a DNS is made after review of a completed environmental checklist and other information on file with the lead agency. The pertinent documents are available to the public on request. WAC 197-11-970.

If the lead agency determines that the proposal will have no probable significant adverse environmental impacts, the agency must prepare and issue a DNS substantially in the form provided in WAC 197-11-970. WAC 197-11-340.

The agency must send the DNS and environmental checklist to agencies with jurisdiction, the Washington State Department of Ecology, affected tribes, and each local agency or political subdivision whose public services would be changed as a result of implementation of the proposal. WAC 197-11-340.


9-WA-b.13 to 9-WA-b.14 – Provide Notice of DNS and Allow for Comment

Notice of completion of a DNS must be effectuated using the SEPA procedures set forth by the lead agency. Public notice of the DNS is required. The lead agency is responsible for providing reasonable notice to the public, and they are permitted to use their own form of notice for this purpose. WAC 197-11-510. Members of the public have 30 days to comment on the DNS. The lead agency may extend the comment period by 15 days if such an extension is requested before the end of the comment period. WAC 197-11-502; WAC 197-11-455.


9-WA-b.15 – Modify DNS and Conduct Hearing (If Necessary)

A public hearing may be held if the lead agency determines that it would assist in determining environmental impacts or if fifty or more persons residing in the lead agency’s jurisdiction request a hearing. If a public hearing is held, it must be open to the consideration of the environmental impact of the proposal, together with the DNS. WAC 197-11-535.

The lead agency must reconsider the DNS based on timely comments and may retain or modify the DNS. The lead agency may withdraw the DNS if it determines that significant adverse impacts are likely. When the DNS is modified, the lead agency must send the modified DNS to agencies with jurisdiction.


9-WA-b.16 – Final DNS

Following review of the draft DNS, the lead agency will modify the DNS as necessary and issue a final DNS. The final DNS must take the form outlined in WAC 197-11-970.


9-WA-b.17 to 9-WA-b.18– Does Another Agency Assume Lead Agency Status?

Assumption of lead agency status occurs when the original lead agency issues a DNS and another agency with jurisdiction believes that the proposed project is likely to have significant adverse environmental impacts and that an EIS is needed to evaluate those impacts. After assuming lead agency status, the new lead agency is then required to issue a determination of significance and prepare an environmental impact statement. WAC 197-11-948. For more information, see:

State Environmental Impact Statement:
9-WA-c


9-WA-b.19 – Appeal Decision (If Applicable)

Each lead agency decides whether or not to offer an administrative appeals process. However, if the lead agency does permit administrative appeals, the procedures must comply with those set out in WAC 197-11-680(3)(a). Any individual wishing to appeal the DS or DNS must first go through the administrative appeals process, if the lead agency provides one. RCW 43.21C.075(4); WAC 197-11-680(3)(c). If the lead agency does not provide an administrative appeals process, the individual wishing to appeal may initiate a judicial appeal. WAC 197-11-680(4).



Agencies

No agencies provided.

| Add an Agency


Contact Information

| Add a Contact




Print PDF



Edit Washington State Department of Ecology
State Environmental Issues Contact
360.407.6004
franabbazabbasant@ecyabbazabbawaabbazabbagov