This flowchart illustrates the process for distributed generation (DG) interconnection in the state of Texas. The DG interconnection rules, developed by the Public Utility Commission of Texas, set forth the rights and responsibilities of both the DG developer and the transmission distribution utility (TDU).


Distributed Generation Interconnection Process

8-TX-f.1 – Application for Interconnection of Distributed Generation

General Requirements for Distributed Generation include:

  • Developer’s generation and interconnection installation must meet all applicable national, state, and local construction and safety codes;
  • Developer’s generator must be equipped with protective hardware and software designed to prevent the generator from being connected to a de-energized circuit owned by the utility;
  • Developer’s generator must be equipped with the necessary protective hardware and software designed to prevent connection or parallel operation of the generating equipment with the utility system unless the utility system service voltage and frequency is of normal magnitude;
  • Developer may install pre-certified equipment on their utility systems in accordance with an approved interconnection control and protection scheme without further review of their design by the utility. When the developer is exporting to the utility system using pre-certified equipment, the protective settings and operations shall be those specified by the utility;
  • Developer is responsible for protecting its generating equipment in such a manner that utility system outages, short circuits or other disturbances including zero sequence currents and ferroresonant over-voltages do not damage the customer’s generating equipment. The customer’s protective equipment shall also prevent unnecessary tripping of the utility system breakers that would affect the utility system’s capability of providing reliable service to other customers;
  • For facilities greater than two MW, the utility may require that a communication channel be provided by the customer to provide communication between the utility and the developer’s facility;
  • Circuit breakers or other interrupting devices at the point of common coupling must be capable of interrupting maximum available fault current. Facilities larger than two MW and exporting to the utility system shall have a redundant circuit breaker unless a listed devise suitable for the rated application is used; and
  • Developer will furnish and install a manual disconnect device that has a visual break that is appropriate to the voltage level, and is accessible to the utility personnel, and capable of being locked in the open position. Developer must follow the utility’s switching, clearance, tagging, and locking procedures, which the utility must provide for the developer.

8-TX-f.2 – Review Application Materials for Completeness

Upon receipt of a completed application, the TDU has a 4-6 week period in which to process the application and provide the following:

  • Approval to interconnect;
  • Approval to interconnect with a list of prescribed changes to the DG design;
  • Justification and cost estimate for prescribed changes to TDU system; or
  • Application rejection with justification

8-TX-f.3 – Is the Application Complete?

Developers must provide all necessary information with their application. Failure to supply all necessary information is grounds for rejection of the application.

8-TX-f.4 – Declare Application Administratively Complete

The TDU will have its engineering staff evaluate completed applications to determine whether pre-interconnection studies are required.

8-TX-f.5 – Is the Facility to be Located on a Networked Secondary Distribution System?

Developers and the TDU must use best reasonable efforts to complete the interconnection process in instances where developers request interconnection to a secondary network system. Certain aspects of secondary network systems create technical problems that may make interconnection more costly to implement.

8-TX-f.6 – Conduct Secondary Network Review

In a network secondary distribution system, service is redundantly provided through multiple transformers as opposed to radial systems where there is only one path for power to flow from the distribution substation

The TDU must utilize the following guidelines when overseeing a secondary network interconnection:

  • The TDU must approve applications for distributed generation facilities that use inverter-based protective functions unless total distributed generation (including the new facility) on affected feeders represents more than 25% of the total load of the secondary network under consideration;
  • The TDU must approve applications for other on-site generation facilities whose total generation is less than the local customer’s load unless total distributed generation (including the new facility) on affected feeders represents more than 25% of the total load of the secondary network under consideration;
  • The TDU may postpone processing an application for an individual distributed generation facility if the total existing distributed generation on the targeted feeder represents more than 25% of the total load of the secondary network under consideration. If that is the case, the TDU should conduct interconnection and network studies to determine whether, and in what amount, additional distributed generation facilities can be safely added to the feeder or accommodated in some other fashion. These studies should be completed within six weeks, and application processing should then resume;
  • The TDU may reject applications for a distributed generation facility under this section if the TDU can demonstrate specific reliability or safety reasons why the distributed generation should not be interconnected at the requested site. However, the TDU must work with developers to resolve such problems to their mutual satisfaction.
  • The TDU must make all reasonable efforts to seek methods to safely and reliably interconnect distributed generation facilities that will export power. This may include switching service to a radial feed if practical and if acceptable to the customer.

8-TX-f.7 – Conduct DG Pre-Certification Review

If the DG qualifies as pre-certified under Texas’ pre-certification requirements, the review can proceed to the DG Capacity Review. If the DG does not qualify as pre-certified, the TDU is allowed up to six weeks to perform a study that may involve a fee.

8-TX-f.8 – Conduct DG Capacity Relative to Load

Secondary networks are used where load is sufficiently dense to justify the added reliability and added cost of such a system.

PUCT Substantive Rule 25.211(h)(1) and (2) define when the TDU must approve applications for interconnection (the TDU may elect to do a study but may not charge a fee):

  • DG facilities that use inverter-based protective functions with total distributed generation (including the new facility) on the affected secondary network representing no more than 25% of the total load of that network.
  • Other on-site generation facilities whose total generation is less than the local customer’s load (non-export) and with total distributed generation (including the new facility) on affected secondary network representing no more than 25% of the total load of that network.

The TDU will compare the total network load to the total DG capacity in order to determine whether installation of the DG will require costly changes to the utility system. If the DG installation will not result in costly changes, then a study fee will not be charged because it is assumed that no study is necessary. It is assumed that all inverter-bad DG under 20kW is so small that, irrespective of the 25% threshold, no study is necessary and therefore the application must be accepted and no study fee may be charged.

8-TX-f.9 – Conduct Power Export Review

The TDU must determine whether the DG will export power in order to ensure that the DG complies with PUCT Substantive Rule 25.211(h)(2). All export systems on network secondaries may be subject to a study for which a fee may be charged.

Any DG system designed for non-export will not adversely impact the secondary network protection schemes and, for systems with explicit non-export capabilities, the need for additional protections is eliminated.

Non-inverter-based DG that does not export and meets the 25% threshold should not require changes to the utility system in order to accommodate the installation. The TDU must accept these applications, and a study fee may not be charged since it is assumed that no study is necessary.

If the DG is not inverter-based and is not less than minimum applicant load, but still complies with the 25% threshold, a study fee may be charged to the applicant to determine whether any modifications need to be made. The study can take up to four weeks. If the total DG capacity on a particular network exceeds 25% of the total load of the network, the TDU may halt the application process up to six weeks while performing a study that may involve a study fee. Once the study is complete, the application processing and the allowable processing time will continue.

8-TX-f.10 – Conduct Non-Network Review

Any DG project that is not in a network secondary distribution must go through a Non-Network review.

8-TX-f.11 – Conduct DG Pre-Certification Review

If the DG qualifies as pre-certified, the non-network review can proceed to the DG Capacity Review. If the DG equipment is not pre-certified, a study may be performed that can take up to six weeks and involve a study fee.

8-TX-f.12 – Conduct DG Capacity Review

If the DG capacity is less than or equal to 500kW, the review can continue to the export level review. If the DG capacity exceeds the 500kW threshold, the TDU is allowed up to four weeks to perform a study that may involve a fee.

8-TX-f.13 – Conduct Export Level Review

If developers will export power across the point of common coupling (PCC):

  • The TDU may need to study the local distribution system and determine if adjustments to local voltage regulation schemes are necessary to avoid reverse voltage drops; and
  • If the DG system falls within a specified export limit, it is assumed by the TDU that the application of the DG on that portion of the distribution system will not cause complications. DG which exceeds the threshold may be studied to determine whether it could cause islanding or adverse power flows.

8-TX-f.14 – Approve Distributed Generation Interconnection

The TDU is obligated to connect DG facilities that comply with the procedures described in the PUCT DG Interconnection Manual and the technical requirements of PUCT Substantive Rule 25.212.

A TDU does not have the right to unilaterally refuse to connect a DG project. The TDU is required to document the technical or business reasons for not granting a DG application as filed, and is obligated to work with the developer to resolve any problems to the satisfaction of both parties.

If the TDU believes that although a specific DG application meets the PUCT's technical requirements for system safety and reliability, but the costs of reconfiguring the TDU system to accomodate the new DG unit appear excessive, the TDU may seek guidance from the PUCT before approving or denying the DG application.