The power plant's location, size, type of customer the power plant sells energy to, and whether the power plant sells energy in "interstate commerce" will determine what permits the facility requires. Siting procedures can be complex and contentious, especially when a proposed facility conflicts with other land uses, or is proposed in environmentally or culturally sensitive areas. Building a power plant usually requires permission from local, tribal, state or federal government entities. If the plant will be located on state land, the developer may be required to follow a state energy facility siting procedure. The process for obtaining a permit on state land differs from state-to-state, but each generally includes an application process, a time for public comment, and a process for appeals.


As an initial matter, under the Federal Power Act the Federal Energy Regulatory Commission has authority over “public utilities,” which under 16 USC 824(e) includes any person who owns or operates facilities subject to jurisdiction of FERC, which includes any person who owns or operates a facility for the transmission of electric energy in interstate commerce and to the sale of electric energy at wholesale in interstate commerce. Interstate commerce has been interpreted broadly to include when the transmission system is interconnected and capable of transmitting electric energy across the state boundary, even if the contracting parties and the electrical pathway between them are in one state. See Florida Power & Light Company, 29 FERC, ¶ 61, 140 at 61, 291-92 (1984).


Power Plant Siting, Construction, and Regulation Overview Process

7.1 to 7.3 – Will the Power Plant Be Constructed on Federal Lands?

Geothermal

If the power plant will be located on federal land, the developer will be required to go through a Utilization Application Process. This process involves the development of a Utilization Plan. The developer will be required to submit a Utilization Plan, Operation Plan, and Draft Facility Construction Permit to the Bureau of Land Management (BLM). The plant commissioning process follows the implementation of a Utilization Plan.

Utilization Application Process:
7-FD-a

If the power plant will be constructed on state lands, the developer will initiate a state specific energy facility siting and construction process.

California

In California, the California Energy Commission (CEC) has authority to license thermal power plants with a net generating capacity of fifty (50) megawatts (MW) or more and all related facilities dedicated or essential to the operation of thermal power plants. For more information, see:

State Plant Commissioning Process, Application for Certification:
7-CA-a

Hawaii

In Hawaii, may need a Geothermal and Cable System Development Permit to build a geothermal power plant and then transmit the energy to another island through an inter-island deep water transmission cable system. For more information, see:

Geothermal and Cable System Development Permit:
7-HI-a

Montana

In Montana, a developer must obtain a Certificate of Compliance to construct a geothermal generating facility with the capacity of producing fifty (50) MW or more. For more information, see:

Energy Facility Siting:
7-MT-a

Oregon

In Oregon, a developer may need approval from the Oregon Siting Board for the development of a geothermal facility. For more information, see:

State Plant Construction:
7-OR-a

Texas

In Texas, a developer may need to register a geothermal facility with the Public Utility Commission of Texas. For more information, see:

Washington

Energy Facility Registration:
7-TX-a

In Washington, a developer may not begin construction of a new energy facility without an Energy Facility Siting Certification form the Washington State Energy Facility Evaluation Council. For more information, see:

Power Plant Siting Process:
7-WA-a

Solar

If the power plant will be constructed on federal lands, the developer will initiate the Land Access Process Overview.

Land Access Process Overview: 3


If the power plant will be constructed on state lands, the developer will initiate a state specific energy facility siting and construction process.


7.4 to 7.5 – Is the Facility a Cogeneration Facility or a Small Power Production Facility?

If the facility is a cogeneration facility or a small power production facility the developer may apply for certification as a Qualifying Facility under Public Utilities Regulatory Policy Act (PURPA). A cogeneration facility is a generating facility that sequentially produces electricity and another form of useful thermal energy (such as heat or steam) in a way this is more efficient than the separate production of both forms of energy. A small power production facility is a generating facility that is 80 megawatts or less with a primary energy source (i.e. at least 75%) of hydro, wind, solar, biomass, waste, or geothermal resources.

Qualifying Facilities receive special rate and regulatory treatment. Qualifying Facilities have the right to sell energy to public utilities at the "avoided cost" rate (i.e. the cost to the public utility to produce the energy itself), provided FERC has not relieved the utility from its purchase obligation under 18 CFR 292.309. Under USC 824a-3(m) after August 8, 2005, no electric utility shall be required to enter into a new contract or obligation to purchase electric energy from a qualifying cogeneration facility or a qualifying small power production facility if FERC finds that the qualifying cogeneration facility or qualifying small power production facility has nondiscriminatory access to:

  • Independently administered, auction-based day ahead and real time wholesale markets for the sale of electric energy wholesale markets for long-term sales of capacity and electric energy; or
  • Transmission and interconnection services that are provided by a FERC approved regional transmission entity and administered pursuant to an open access transmission tariff that affords nondiscriminatory treatment to all customers and competitive wholesale markets that provide a meaningful opportunity to sell capacity, including long-term and short-term sales, and electric energy, including long-term, short-term and real-time sales, to buyers other than the utility to which the qualifying facility is interconnected. In determining whether a meaningful opportunity to sell exists, the Commission shall consider, among other factors, evidence of transactions within the relevant market; or
  • Wholesale markets for the sale of capacity and electric energy that are, at a minimum, of comparable competitive quality as markets described in the options above.

Qualifying Facilities also have the right to purchase supplementary power, backup power, maintenance power, and interruptible power at reasonable rates from public utilities. Finally, certain Qualifying Facilities, including eligible solar and geothermal small power production facilities that produce electric energy solely by using any combination of biomass, waste, hydro, wind, solar, or geothermal resources as a primary energy source and has a power production capacity no greater than 80(MW), are exempt from specific statutes and regulations. The exemptions include:

  • The Public Utility Holding Company Act of 2005 (PUHCA);
  • The Federal Power Act (expect sections 205 and 206 on "just and reasonable" rate approval); and
  • State laws and regulations respecting the rates and financial and organizational aspects of utilities.
Note - Qualifying Facilities under 20 megawatts are exempt from the entire Federal Power Act, including sections 205 and 206.

PURPA Qualifying Facility Certification Process:
7-FD-c

7.6 to 7.7 – Is the Facility an Independent Power Producer That Exclusively Sells to Wholesale Customers?

If the power plant is an independent power producer, the plant may be exempt from certain federal regulations. The Energy Policy Act of 1992 created an exemption from the Public Utility Holding Company Act (PUHCA) for ‘Exempt Wholesale Generators’ (EWG). EWGs include independent power producers that sell energy only to wholesale customers. For EWGs to maintain their status they must restrict sale agreements to wholesale sales. Like, Qualifying Facilities over 20 megawatts, EWGs are subject to FERC regulations on rate approval under section 205 of the Federal Powers Act. However, unlike Qualifying Facilities, EWGs may not take advantage of retail sale opportunities in local jurisdictions.

Exempt Wholesale Generator Status Process:
7-FD-d

7.7 to 7.9 – Will the Facility Require a CPCN from a State Public Utility Regulatory Authority?

If the state public utility regulatory authority regulates the facility, the facility may need a Certificate of Public Convenience and Necessity (CPCN). The CPCN generally is necessary to establish a public need for the facility and the developer’s ability to fill that need. Some states do not regulate independent power producers if they do not sell power directly to the public because the state only regulates developers that fall within the states’ definition of “public utility”. Developers who are also public utilities will be regulated by the state utility regulatory authority and will likely be required to obtain a CPCN.

Alaska

Under Alaska Statutes 42.05.211 a public utility may not operate and receive compensation for providing a commodity or service without first obtaining a Certificate of Public Convenience and Necessity from the Regulatory Commission of Alaska.

Alaska defines "public utility' in Alaska Statutes 42.05.990 (5) to include every corporation whether public, cooperative, or otherwise, company, individual, or association of individuals, their lessees, trustees, or receivers appointed by a court, that owns, operates, manages, or controls any plant, pipeline, or system for furnishing, by generation, transmission, or distribution, electrical service to the public for compensation.

Certificate of Public Convenience and Necessity:
7-AK-c

California

Any electric public utilities proposing to construct an electric generating facility 50 MW or greater (including any electrical corporation as defined in California Public Resource Code Section 218(a) and (b)) that performs a service for, or delivers a commodity to, the public or any portion thereof for which any compensation or payment is received is a public utility subject to California Public Utilities Commission and must apply for a Certificate of Public Convenience and Necessity under General Order 131-D Section III. Additionally, when any person or corporation performs any service for, or delivers a commodity to, any person, private corporation, municipality, or other political subdivision of the state, that in turn either directly or indirectly, mediately or immediately, performs that service for, or delivers that commodity to, the public or any portion thereof, is also a public utility subject to California Public Utilities Commission and must apply for a Certificate of Public Convenience and Necessity under General Order 131-D Section III to construct an electric generating facility 50 MW or greater.


California Energy Facility CPUC Process:
7-CA-c

Hawaii

Under Hawaii Revised Statutes 269-7.5 no public utility may commence its business without first having obtained from the Hawaii Public Utilities Commission a Certificate of Public Convenience and Necessity.

Hawaii defines "public utility" in Hawaii Revised Statues 269-1 to include every person who may own, control, operate, or manage…any plant or equipment, or any part thereof, directly or indirectly for public use…for production, conveyance, transmission, delivery, or furnishing of light, power, heat, cold, water, gar, or oil. However, the definition of public utility does not include any user, owner, or operator of the Hawaii Electric System. Hawaii Revised Statutes 269-141 defines "User, owner, or operator of the Hawaii electric system" as any person, business, organization, or other entity who:

(1) Owns, controls, operates, or manages plants or facilities for the generation, transmission, or furnishing of electricity; and
(2) Provides, sells, or transmits all of that electricity, except such electricity as is used in its own internal operations or is used for its own consumption, directly to a public utility for either transmission or distribution to the public.


Certificate of Public Convenience and Necessity:
7-HI-c

Idaho

Under Idaho Statues 61-526 no electrical corporation may begin construction of a line, plant or system or any extension of a line, plant, or system, without first obtaining a Certificate of Public Convenience and Necessity (CPCN) from the Idaho Public Utilities Commission. Electrical corporations do not need a CPCN for an extension within any city or county, within which it has theretofore lawfully commenced operations, or for an extension into territory whether within or without a city or county, contiguous to its line, plant or system, and not theretofore served by a public utility of like character, or for an extension within or to territory already served by it necessary in the ordinary course of its business.

Idaho defines "electrical corporation" in Idaho Statutes 61-119 to include every corporation or person, their lessees, trustees, receivers or trustees appointed by any court whatsoever, owning, controlling, operating or managing any electric plant for compensation within this state, except where electricity is generated on or distributed by the producer through private property alone, solely for his own use or the use of his tenants and not for sale to others, and excepting also, where the electricity is to be used exclusively in operations incident to the working of metalliferous mines and mining claims, mills, or reduction and smelting plants, and the transmission lines and distribution systems are owned by the consumer or where several consumers severally own their individual distribution systems and jointly own, in their own names or through a trustee, the transmission lines used in connection therewith and transmit such electricity, whether generated by themselves or procured from some other source, over such transmission lines and distribution systems without profit, and to be used for their private uses for the purposes aforesaid in places outside the limits of incorporated cities, towns and villages, and not for resale or public use, sale or distribution.

Certificate of Public Convenience and Necessity:
7-ID-c

Nevada

Under Nevada Revised Statutes 704.865 a person, other than a local government, may not begin to construct a utility facility in the Nevada without first having obtained a permit from the Public Utilities Commission of Nevada. The replacement of an existing facility with a like facility, as determined by the Public Utilities Commission of Nevada, does not constitute construction of a utility facility. Any facility, with respect to which a permit is required, must thereafter be constructed, operated and maintained in conformity with the permit and any terms, conditions and modifications contained therein. A permit may only be issued pursuant to NRS 704.820 to 704.900, inclusive. Any authorization relating to a utility facility granted under other laws administered by the Commission constitutes a permit under those sections if the requirements of those sections have been complied with in the proceedings leading to the granting of the authorization.

Nevada defines a “utility facility” in Nevada Revised Statues 704.860 as electric generating plants and their associated facilities, except electric generating plants and their associated facilities which use or will use renewable energy, as defined in NRS 704.7811, as their primary source of energy to generate electricity and which have or will have a nameplate capacity of 70 megawatts or less, including, without limitation, a net metering system, as defined in NRS 704.771. “Associated facilities” includes, without limitation, any facilities for the storage, transmission or treatment of water, including, without limitation, facilities to supply water or for the treatment or disposal of wastewater, which support or service an electric generating plant.

State PUC Process:
7-NV-c

Utah

Under Utah Code 54-4-25, any "electric corporation, telephone corporation, telegraph corporation, heat corporation, water corporation, or sewerage corporation may not establish, or begin construction or operation of a line, route, plant, or system or of any extension of a line, route, plant, or system, without having first obtained from the commission a certificate that present or future public convenience and necessity does or will require the construction."

Utah defines "electrical corporation in Utah Code 54-2-1(7) to include every corporation, cooperative association, and person, their lessees, trustees, and receivers, owning, controlling, operating, or managing any electric plant, or in any way furnishing electric power for public service or to its consumers or members for domestic, commercial, or industrial use, within this state, except independent energy producers, and except where electricity is generated on or distributed by the producer solely for the producer's own use, or the use of the producer's tenants, or for the use of members of an association of unit owners formed under Title 57, Chapter 8, Condominium Ownership Act, and not for sale to the public generally, and except where the electricity generated is consumed by an owner, lessor, or interest holder, or by an affiliate of an owner, lessor, or interest holder, who has provided at least $25,000,000 in value, including credit support, relating to the electric plant furnishing the electricity and whose consumption does not exceed its long-term entitlement in the plant under a long-term arrangement other than a power purchase agreement, except a power purchase agreement with an electrical corporation.

Utah defines an "independent energy producer" as every electrical corporation, person, corporation, or government entity, their lessees, trustees, or receivers, that own, operate, control, or manage an independent power production or cogeneration facility. Utah Code 54-2-1(15).

Utah defines an "independent power production facility as a facility that produces electric energy solely by the use, as a primary energy source, of biomass, waste, a renewable resource, a geothermal resource, or any combination of the preceding sources or is a qualifying power production facility. Utah Code 54-2-1(16).


Utah Public Service Commission:
7-UT-c

Colorado

Any public utility seeking to construct and operate a facility or an extension of a facility must file an application for a Certificate of Public Convenience and Necessity.

Certificate of Public Convenience and Necessity:
7-CO-c

Texas

Under Texas Utilities Code Sec. 37.051, an electric utility or other person may not provide service to the public unless they first obtain from the Public Utility Commission of Texas a certificate that states that the public convenience and necessity requires or will require the installation, operation, or extension of the service. Additionally, a retail electric utility may not furnish retail electric utility service to an area in which retail electric service is being lawfully furnished by another retail electric utility unless the utility first obtains a certificate of convenience and necessity.

A "retail electric utility" means a person, political subdivision, electric cooperative, or agency that operates, maintains, or controls in this state a facility to provide retail electric utility service.

If a power producer is not a "retail electric utility" then the developer is not required to obtain a certificate of convenience and necessity for the power plant. Otherwise, a certificate of convenience and necessity is required for new generating units and new electric transmission lines.

Certificate of Convenience and Necessity:
7-TX-c

New Mexico

In New Mexico, any “public utility” that seeks to provide electricity for the public must obtain a Certificate of Public Convenience and Necessity (CPCN) from the New Mexico Public Regulation Commission (“Commission”). Under the New Mexico Public Utility Act, a “public utility” or “utility” means every person not engaged solely in interstate business and that may own, operate, lease or control any plant, property or facility for the generation, transmission or distribution, sale or furnishing to or for the public of electricity for light, heat or power or other uses. 62-3-3(G)(1).

Certificate of Convenience and Necessity:
7-NM-c