This flowchart illustrates the procedures required of developers in Nevada when dealing with biological considerations. The Nevada Department of Wildlife (NDOW) oversees implementation of state biological resources considerations in Nevada.

Nevada has a particular state notification and review process for wildlife considerations for all energy projects 10 megawatts or greater. The process is governed by NRS 701.600 et seq. Developers may also choose to establish a Habitat Conservation Plan for their project in order to facilitate cooperation with NDOW. If the project will disturb wildlife, then the developer may be required to obtain an Incidental Take Permit from NDOW.

For more information see the Nevada Department of Wildlife Energy Planning and Conservation Fund Website.

State Biological Resource Considerations Process

12-NV-a.1 to 12-NV-a.2 – Does the Project Require a Notice of Energy Development Project?

If the developer files an application with the federal government for a lease or easement for a right-of-way for an energy development project or an application with the Public Utilities Commission of Nevada or any county in Nevada relating to the construction of an energy development project must, concurrently with the filing of the application, file a Notice of Energy Development Project with and provide an initial fee to the Nevada Department of Wildlife (NDOW). NRS 701.610(1). If the project is under 10 MW, then the developer is not required to provide notice to NDOW.

12-NV-a.3 - Notice of Energy Development Project

The developer is required to provide NDW with notice of the development of an energy project (Nevada Department of Wildlife Application for Energy Projects "Fund for the Recovery of Costs") if the project will produce over 10MW. The notice must include the following:

  • A description of the location and the energy development project to be built thereon;
  • A description of the boundaries of the project and estimated requirements for infrastructure of the project; and
  • The estimated energy output for the energy development project. NRS 701.610(2).

12-NV-a.4 – Forward Notice of Energy Development Project

NDOW is required to provide a copy of the Notice of Energy Development Project to the Nevada Office of Energy within 30 days after the notice is filed. NRS 701.610(3).

12-NV-a.5 – Provide Written Estimate of Anticipated Additional Reimbursement Costs

Nevada has a recoupment program to reimburse the Nevada Department of Wildlife (NDOW) for the cost of consultation. The developer pays a particular recoupment fee before consultation with NDOW begins. After the fee/deposit is paid, NDOW then consults with the developer and other state and federal agencies (as required) to determine the impact of the project on wildlife. Following consultation, NDOW prepares an accounting of their costs and reimburses the developer any balance due. NDOW is not permitted to seek reimbursement for costs incurred as a result of requests from the federal government or the Nevada Public Utilities Commission.

Cost recovery for energy projects is most common when the project requires environmental review under the National Environmental Policy Act (NEPA).

12-NV-a.6 – Does the Developer Dispute Reimbursement Costs?

The regulations contain a detailed appeals process for developers to dispute the assessed costs. Final decisions by the Director of the Department of Wildlife may be appealed to state court.

12-NV-a.11 - Habitat Conservation Plan

The developer has the option to enter into a habitat conservation plan with the assistance of NDOW. The habitat conservation plan is voluntary, but could serve as good faith in the event an unanticipated impact on a species occurs.

Examples of Habitat Conservation Plans in Nevada. Additional information on Habitat Conservation Plans in Nevada can be found on the Nevada Fish & Wildlife’s Habitat Conservation Plan webpage.

12-NV-a.12 to 12-NV-a.14 - Incidental Take Permit

Nevada Department of Wildlife sponsors an incidental take program that is similar to the federal program under the Endangered Species Act. The developer has the option to apply for an incidental take permit in the event the developer anticipates the possibility of an unintended harm to a protected species. NDOW has exclusive authority to either grant or deny the incidental take permit application. Protected, threatened and sensitive animals are listed in NAC 503.

12-NV-a.15 - Written Request for Hearing filed with the Director of Nevada Department of Wildlife

When a dispute arises with regards to the recovery costs requested by the NDOW, the developer may request a hearing with the Director of Nevada Department of Wildlife within 20 days after a decision from the NDOW.

12-NV-a.16 to 12-NV-a.18 – Set a Hearing

The Director will conduct a hearing and accept evidence of additional costs.

12-NV-a.19 - Final decision

The Director will make a final decision based on the evidence presented. The developer may appeal the decision to state court.

Contact Information

| Add a Contact

Print PDF

Edit Nevada Department of Wildlife
State Flora and Fauna Considerations Contact
Visit Website

Edit Nevada Department of Wildlife
State Flora and Fauna Considerations Contact #2

Visit Website