Project Profile
Project Start Date 1/1/2012

Project Country Canada
Project Resource
Click here
Current /Tidal
Project Nearest Body of Water St Lawrence River
Coordinates 45.5519°, -73.5152°

Project Phase Phase 1

Project Details The primary focus for the deployment of the "SR-01" is Canada’s Far North, and it is therefore suited to extreme climate conditions.

Permit/License Buildout (MW) 0
Device Nameplate Capacity (MW) 2

Main Overseeing Organization Sabella Energy

Project Technology MHK Technologies/Sabella River Generator

Project Licensing
Environmental Monitoring and Mitigation Efforts See Tethys