MHK Projects/OWC Pico Power Plant

Jump to: navigation, search

<< Return to the MHK database homepage

Loading map...
Project Profile
Project Start Date 1/1/1998


Project City Cachorro Pico Island, Azores

Project Country Portugal
Project Resource
Click here
Current /Tidal

Coordinates 38.5609°, -28.4682°

Project Phase Phase 4

Project Details Construction of the OWC Pico Power Plant project started in 1995 under the coordination of Instituto Superior Tecnico, and was commissioned in 1999. However, the plant was virtually unoperated until a recovery project started in 2003 under the auspices of the Wave Energy Centre, and began operating again in 2005.
Project Installed Capacity (MW) 0

Device Nameplate Capacity (MW) 400kW

Number of Devices Deployed 1




Main Overseeing Organization Wave Energy Centre

Project Technology MHK Technologies/European Pico Pilot Plant

Project Licensing
Environmental Monitoring and Mitigation Efforts See Tethys

<< Return to the MHK database homepage