Project Start Date 1/1/2004


Project City Kvalsundet Strait near Troms, NULL

Project Country Norway
Project Resource
Click here
Current /Tidal

Coordinates 69.8079°, 18.6795°

Project Phase Phase 1

Project Details In 2004, Statkraft signed an agreement with Hydra Tidal to oversee the joint development and construction of a full-scale demonstration plant. The main objective of the MORILD project is to demonstrate the functionality and overall efficiency of a full-scale, operational tidal power plant.
Project Installed Capacity (MW) 1

Device Nameplate Capacity (MW) 1 25 MW

Number of Devices Deployed 1




Main Overseeing Organization Hydra Tidal Energy Technology AS

Project Technology MHK Technologies/Morild Power Plant

Project Licensing
Environmental Monitoring and Mitigation Efforts See Tethys