Project Profile
Project Start Date 1/1/2009


Project City Hayle, Cornwall
Project Country United Kingdom
Project Resource
Click here
Wave
Coordinates 50.1853°, -5.4208°
Project Phase Phase 2
Project Details Oceanlinx has signed Letter of Intent with South West of England Regional Development Agency (SWRDA) for a 5 MW facility as part of the Cornwall Wave Hub.
Project Installed Capacity (MW) 5
Permit/License Buildout (MW) 5
Device Nameplate Capacity (MW) For utility uses 40kW to 150kW with 500kW in the development phase
Number of Devices Deployed 0
Number of Build Out Units Deployed 10


Main Overseeing Organization Ocean Power Technologies
Project Technology MHK Technologies/PowerBuoy
Project Timeline and Milestones •7/15/2009 Commitment agreement signed for Wave Hub
•7/30/2010 Cable installation commences
•7/30/2011 Cable Installation completed