Delaware River Basin Commission (Multiple States)

This is the approved revision of this page, as well as being the most recent.
Jump to: navigation, search

Last modified on February 12, 2015.

EZFeed Policy

Place Delaware;New Jersey;Pennsylvania;New York

Applies to States or Provinces Delaware;New Jersey;New York;Pennsylvania
Name Delaware River Basin Commission (Multiple States)
Policy Category Other Policy
Policy Type Environmental Regulations, Siting and Permitting
Affected Technologies Biomass/Biogas, Coal with CCS, Hydroelectric, Hydroelectric (Small), Natural Gas, Nuclear
Active Policy Yes

Implementing Sector State/Province

Start Date 1961

Program Administrator Delaware River Basin Commission
Primary Website
Applicable Jurisdiction Delaware River Basin

Last Review 2014-09-15


The Delaware River Basin Commission (DRBC) is a federal-interstate compact government agency that was formed by concurrent legislation enacted in 1961 by the United States and the four basin states (Pennsylvania, New York, New Jersey, and Delaware). Its five members include the basin state governors and the Division Engineer, North Atlantic Division, U.S. Army Corps of Engineers, who serves as the federal representative. The commission has legal authority over both water quality and water quantity-related issues throughout the basin.

Much of the new drilling interest taking place in northeastern Pennsylvania and southern New York is targeted at reaching the natural gas found in the Marcellus Shale formation, which underlies about 36 percent of the Delaware River Basin.

In connection with natural gas drilling, the commission has identified three major areas of concern:

1) Gas drilling projects in the Marcellus Shale or other formations may have a substantial effect on the water resources of the basin by reducing the flow in streams and/or aquifers used to supply the significant amounts of fresh water needed in the natural gas mining process. 2) On-site drilling operations may potentially add, discharge or cause the release of pollutants into the ground water or surface water. 3) The recovered "frac water" must be treated and disposed of properly.

While the Delaware River itself is un-dammed, there are 13 dams within the basin that feed into the river. The Commission holds authority to approve any project that will have a substantial effect on the water resources of the basin.

The Commission also has approval authority over energy projects that need to draw water from the basin, including coal plants, biomass plants, and natural gas extraction and power plants.

Policy Contact

Contact Name Victoria Lawson
Department Project Review Section

Phone 609-883-9500 ext. 216