Application Filling Requirements for Transmission Line and Substation Construction Projects (Wisconsin)

This is the approved revision of this page, as well as being the most recent.
Jump to: navigation, search


Last modified on February 12, 2015.

EZFeed Policy

Place Wisconsin


   

Name Application Filling Requirements for Transmission Line and Substation Construction Projects (Wisconsin)
Policy Category Other Policy
Policy Type Siting and Permitting
Affected Technologies Biomass/Biogas, Coal with CCS, Concentrating Solar Power, Energy Storage, Fuel Cells, Geothermal Electric, Hydroelectric, Hydroelectric (Small), Natural Gas, Nuclear, Solar Photovoltaics, Wave Energy, Wind energy
Active Policy Yes

Implementing Sector State/Province



























Program Administrator Public Service Commission of Wisconsin
Primary Website http://psc.wi.gov/utilityInfo/electric/construction/transmissionLineRequirements.htm



Last Review 2014-09-15



Summary

This page describes application requirements for all projects that involve the installation of an electricity transmission line or substation that also require either a Certificate of Public Convenience and Necessity (CPCN) or a Certificate of Authority (CA). Applications must include a discussion of general route impacts, distances to sensitive buildings, impacts on residences and commercial and industrial buildings, and impacts on public and tribal lands.



Policy Contact

Department Public Service Commission of Wisconsin

Address P.O. Box 7854

Place Madison, Wisconsin
Zip/Postal Code 53707-7854
Phone (608)266-5481



Website http://psc.wi.gov/aboutUs/contactUs/contactByIssue.htm#energy
     
     


















References